Return Main Menu

Fencing Work Around Solvent Store
Bill Cost
Actual Cost
Profit
Offer12345: Total : Tk.617,725 Material
312,853
12,392
2,424.64 %
Purchase : 2003-04-07 Total : Tk.617,725 Labour
69,437
32,315
114.88%
Bill123456:2003-07-08 Total : Tk.613,065 Equipment
9,056
0
0.00%
Certify123: 2003-07-10 Total : Tk.523,127 Other
172,874
0
0.00 %
Pay 12345: Total : Tk.0 Overhead
30,886
0
0.00 %
oh: 5.0% Profit:10.0% vat:4.5% it:4.0 % Total Profit =1271.29% Total
595,106
44,707
1231.12 %
Photograph Taken : Start : Finish :84.69%
Code
Item
Unit
BOQ Qty
Bill Qty
Actual Qty
Supp Qty
BOQ Rate
Actual Rate
BOQ Cost
Bill Cost
Actual Cost
Materials-Civil
A101 Filling Sand
0
17
0
0
7.00
0.00
0
120
0
A102 Brick
0
1,033
0
0
3.50
0.00
0
3,614
0
A103 Sand - Local - Mymensingh
0
504
268
0
15.00
10.00
0
7,565
2,675
A104 Polythene
0
5
0
0
77.00
0.00
0
398
0
A105 Cement
0
232
41
0
295.00
237.00
0
68,377
9,717
A106 Sand - Sylhet
278
247
0
0
24.00
0.00
6,675
5,919
0
A107 Stone-chips
1,112
987
0
0
72.00
0.00
80,094
71,032
0
A109 Re-bar - G40
3,675
2,961
0
0
38.50
0.00
141,488
113,999
0
A112 GI Wire
28
23
0
0
90.00
0.00
2,520
2,030
0
 
Total
230,777
273,055
12,392
Material-Paint
A304 Plastron Sealer
15
17
0
0
160.00
0.00
2,368
2,712
0
A306 Enamel paint
7
8
0
0
170.00
0.00
1,258
1,441
0
A307 Snowcel
74
85
0
0
7.60
0.00
562
644
0
A308 Thinner-T6/T7
15
17
0
0
46.00
0.00
681
780
0
A310 Weather Coat (ColorBank)
42
48
0
0
227.85
0.00
9,577
10,970
0
 
Total
14,447
16,548
0
MS/SS Work i/c matr
C201 Gate with MS Pipe-50/25mm
0
93
0
0
250.00
0.00
0
23,250
0
 
Total
0
23,250
0
Equipment-Civil
E102 Mixer m/c and vibrator
1,236
1,096
0
0
7.50
0.00
9,270
8,221
0
E103 Mini Dumper
424
417
0
0
2.00
0.00
848
835
0
 
Total
10,118
9,056
0
Labour - Civil
L000 Form work Foot-col-Str
1,576
1,539
0
0
8.00
0.00
12,607
12,313
0
L001 Re-bar Work
3,500
2,820
2,801
0
1.65
1.65
5,775
4,653
4,622
L002 Formwork upto 10ft from P
2,859
2,339
4,626
0
8.00
6.00
22,871
18,714
27,758
L004 Ordinary Labour Supply
0
19
0
0
100.00
0.00
0
1,934
0
L005 Head Mason Supply
0
2
0
0
200.00
0.00
0
338
0
L015 Carpenter Supply
0
0
-11
0
0.00
120.00
0
0
-1,350
L016 RCC Casting.
812
679
0
0
8.00
4.05
6,498
5,430
0
 
Total
47,751
43,382
31,031
Labour-Civil
L101 Earth Work in Excavation
883
1,236
0
0
1.80
0.00
1,589
2,225
0
L109 Plaster Work
2,960
3,423
0
0
3.00
0.00
8,880
10,268
0
 
Total
10,469
12,492
0
Labour Paints
L602 Weather coat painting
2,960
3,391
0
0
4.00
0.00
11,840
13,563
0
 
Total
11,840
13,563
0
Misc.-Civil
M102 Steel Forms
4,435
3,878
0
0
10.00
0.00
44,348
38,784
0
M105 Shoring for Excavation
339
475
0
0
2.15
0.00
730
1,022
0
M106 Steel Scaffolding
59
68
0
0
100.00
0.00
5,920
6,813
0
M133 Cheisel - Hammer
0
35
0
0
55.00
0.00
0
1,942
0
 
Total
50,998
48,561
0
Sub-contractor-Civil
S112 Turfing
0
2,250
0
0
1.00
0.00
0
2,250
0
 
Total
0
2,250
0
Alum,SS/MS,FalseCeil
S204 GI Fenc i/c MS Pipe-1~1.5
1,830
1,744
0
0
70.00
0.00
128,092
122,064
0
 
Total
128,092
122,064
0
 
Total(1)
504,492
564,221
43,423
Add Overhead on Total(1)
5.0 %
25,225
28,211
Total(2)
529,716
592,432
Add Profit on Total(2)
10.0 %
52,972
59,243
Total(3)
529,716
592,432
Add vat on Total Cost
4.5 %
28,657
32,050
Add Income Tax on Total Cost
4.0 %
28,657
32,050
Total Cost
636,817
712,214