Return Main Menu

ITEM SCHEDULE
Click on Code to see the analysis or Go Home Profit=10%, Overhead=5%, VAT=5.5% IT=5%
D Road Works
Code Item Unit Cost(Tk.) Unit Rate(Tk.)
D01A 50mm Bituminous Carpeting sqm
1091.00
1402
D01B Bituminous Seal Coat sqm
826.00
1061
D01E Box Cutting- Filling Sand-500mm sqm
863.00
1109
D01F Coarse Agreegate Soling-200mm sqm
1687.00
2168
D01D Prime Coat sqm
93.00
119
D01G Scarifying and Cleaning sqm
54.00
69
D01C Tack Coat@7.32 kg bitumin/10m2 sqm
93.00
119