ITEM SCHEDULE | ||||
---|---|---|---|---|
Click on Code to see the analysis or Go Home | Profit=10%, Overhead=5%, VAT=5.5% IT=5% | |||
D | Road Works | |||
Code | Item | Unit | Cost(Tk.) | Unit Rate(Tk.) |
D01A | 50mm Bituminous Carpeting | sqm | 1091.00 |
1402 |
D01B | Bituminous Seal Coat | sqm | 826.00 |
1061 |
D01C | Tack Coat@7.32 kg bitumin/10m2 | sqm | 93.00 |
119 |
D01D | Prime Coat | sqm | 93.00 |
119 |
D01E | Box Cutting- Filling Sand-500mm | sqm | 863.00 |
1109 |
D01F | Coarse Agreegate Soling-200mm | sqm | 1687.00 |
2168 |
D01G | Scarifying and Cleaning | sqm | 54.00 |
69 |