BREAKDOWN OF UNIT PRICE
Item: (K03) Dust Supression-Water Sprinkling
Basis:1 no.
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Unskilled Labour
240.000
no
600.00
144000.00
Sub-Total(L1)
144000.00
144000.00
Total(1)
144000.00
Add over head on Total(1)
5.0 %
7200.00
Total(2)
151200.00
Add Profit on Total(2)
10.0 %
15120.00
Total(3)
166320.00
Add VAT on Unit Price
5.5 %
10220.78
Add Income Tax on Unit Price
5.0 %
9291.62
Unit Price
185832.40
Say
185832
per each