Return Main Menu
BREAKDOWN OF UNIT PRICE
Item: (F009B) 1200mm dia RCC Pipe
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
16.000
no.
15.00
240.00
Sand - Local
1.800
cft
35.00
63.00
Cement
1.000
bag
535.00
535.00
Brick-chips-20mm
3.600
cft
175.00
630.00
Sub-Total(A1)
1468.00
4816.51
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
6.200
cft
4.00
24.80
Excavator
0.005
day
10000.00
50.00
Sub-Total(E1)
74.80
245.42
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brck flat soling
5.340
sft
5.00
26.70
CC Work
6.200
cft
35.00
217.00
RCC Pipe-1200mm dia fit
1.000
rft
250.00
250.00
Sub-Total(L1)
493.70
1619.83
Total(1)
6681.76
Add over head on Total(1)
5.0 %
334.09
Total(2)
7015.84
Add Profit on Total(2)
10.0 %
701.58
Total(3)
7717.43
Add VAT on Unit Price
5.5 %
474.26
Add Income Tax on Unit Price
5.0 %
431.14
Unit Price
8622.83
Say
8623
per RM