BREAKDOWN OF UNIT PRICE
Item: (F008) 450mm dia Rcc pipe (Capital-RC)
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
6.000
no.
15.00
90.00
Sand - Local
0.660
cft
35.00
23.10
Polythene
0.120
kg
105.00
12.60
Cement
0.350
bag
535.00
187.25
Brick-chips-20mm
1.300
cft
175.00
227.50
Sub-Total(A1)
540.45
1773.22
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
2.300
cft
4.00
9.20
Sub-Total(E1)
9.20
30.19
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
4.760
cft
12.00
57.12
Brck flat soling
2.000
sft
5.00
10.00
CC Work
2.300
cft
35.00
80.50
450mm dia RCC pipe
1.000
rft
100.00
100.00
Sub-Total(L1)
247.62
812.44
Total(1)
2615.84
Add over head on Total(1)
5.0 %
130.79
Total(2)
2746.64
Add Profit on Total(2)
10.0 %
274.66
Total(3)
3021.30
Add VAT on Unit Price
5.5 %
185.67
Add Income Tax on Unit Price
5.0 %
168.79
Unit Price
3375.75
Say
3376
per RM