BREAKDOWN OF UNIT PRICE
Item: (F007) 300mm dia Rcc pipe (Capital-RC)
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
4.000
no.
15.00
60.00
Sand - Local
0.500
cft
35.00
17.50
Polythene
0.080
kg
105.00
8.40
Cement
0.250
bag
535.00
133.75
Brick-chips-20mm
0.900
cft
175.00
157.50
Sub-Total(A1)
377.15
1237.43
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
1.500
cft
4.00
6.00
Sub-Total(E1)
6.00
19.69
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
3.170
cft
12.00
38.04
Brck flat soling
1.330
sft
5.00
6.65
CC Work
1.500
cft
35.00
52.50
300mm dia RCC pipe
1.000
rft
75.00
75.00
Sub-Total(L1)
172.19
564.96
Total(1)
1822.07
Add over head on Total(1)
5.0 %
91.10
Total(2)
1913.17
Add Profit on Total(2)
10.0 %
191.32
Total(3)
2104.49
Add VAT on Unit Price
5.5 %
129.33
Add Income Tax on Unit Price
5.0 %
117.57
Unit Price
2351.39
Say
2351
per RM