BREAKDOWN OF UNIT PRICE
Item: (F006) 225mm dia Rcc pipe (Capital-RC)
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
3.000
no.
15.00
45.00
Sand - Local
0.350
cft
35.00
12.25
Polythene
0.065
kg
105.00
6.83
Cement
0.200
bag
535.00
107.00
Brick-chips-20mm
0.700
cft
175.00
122.50
Sub-Total(A1)
293.58
963.22
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
1.200
cft
4.00
4.80
Sub-Total(E1)
4.80
15.75
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
2.380
cft
12.00
28.56
Brck flat soling
1.000
sft
5.00
5.00
CC Work
1.200
cft
35.00
42.00
225mm dia RCC pipe
1.000
rft
50.00
50.00
Sub-Total(L1)
125.56
411.96
Total(1)
1390.93
Add over head on Total(1)
5.0 %
69.55
Total(2)
1460.48
Add Profit on Total(2)
10.0 %
146.05
Total(3)
1606.52
Add VAT on Unit Price
5.5 %
98.72
Add Income Tax on Unit Price
5.0 %
89.75
Unit Price
1795.00
Say
1795
per RM