BREAKDOWN OF UNIT PRICE
Item: (F003) 450 mm dia Rcc pipe (Capital)
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
6.000
no.
15.00
90.00
Sand - Local
0.080
cft
35.00
2.80
Cement
0.045
bag
535.00
24.08
Brick-chips-20mm
0.200
cft
175.00
35.00
Sub-Total(A1)
151.88
498.30
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
5.300
cft
12.00
63.60
Brck flat soling
2.000
sft
5.00
10.00
CC Work
0.300
cft
35.00
10.50
450mm dia RCC pipe
1.000
rft
100.00
100.00
Sub-Total(L1)
184.10
604.03
Total(1)
1102.33
Add over head on Total(1)
5.0 %
55.12
Total(2)
1157.45
Add Profit on Total(2)
10.0 %
115.75
Total(3)
1273.20
Add VAT on Unit Price
5.5 %
78.24
Add Income Tax on Unit Price
5.0 %
71.13
Unit Price
1422.57
Say
1423
per RM