BREAKDOWN OF UNIT PRICE
Item: (F002) 300 mm dia Rcc pipe (Capital)
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
4.000
no.
15.00
60.00
Sand - Local
0.050
cft
35.00
1.75
Cement
0.030
bag
535.00
16.05
Brick-chips-20mm
0.120
cft
175.00
21.00
Sub-Total(A1)
98.80
324.16
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
3.530
cft
12.00
42.36
Brck flat soling
1.330
sft
5.00
6.65
CC Work
0.200
cft
35.00
7.00
300mm dia RCC pipe
1.000
rft
75.00
75.00
Sub-Total(L1)
131.01
429.84
Total(1)
754.01
Add over head on Total(1)
5.0 %
37.70
Total(2)
791.71
Add Profit on Total(2)
10.0 %
79.17
Total(3)
870.88
Add VAT on Unit Price
5.5 %
53.52
Add Income Tax on Unit Price
5.0 %
48.65
Unit Price
973.05
Say
973
per RM