BREAKDOWN OF UNIT PRICE
Item: (F000A) 100mm RCC Pipe
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
2.900
no.
15.00
43.50
Sand - Local
0.500
cft
35.00
17.50
Cement
0.200
bag
535.00
107.00
Brick-chips-20mm
1.000
cft
175.00
175.00
Sub-Total(A1)
343.00
1125.38
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
2.500
cft
12.00
30.00
Brck flat soling
1.000
sft
5.00
5.00
CC Work
1.200
cft
35.00
42.00
RCC Pipe-100mm dia
1.000
rft
30.00
30.00
Sub-Total(L1)
107.00
351.07
Total(1)
1476.45
Add over head on Total(1)
5.0 %
73.82
Total(2)
1550.27
Add Profit on Total(2)
10.0 %
155.03
Total(3)
1705.30
Add VAT on Unit Price
5.5 %
104.79
Add Income Tax on Unit Price
5.0 %
95.27
Unit Price
1905.36
Say
1905
per RM