BREAKDOWN OF UNIT PRICE
Item: (F000) 150mm RCC Pipe
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
3.000
no.
15.00
45.00
Sand - Local
0.540
cft
35.00
18.90
Cement
0.216
bag
535.00
115.56
Brick-chips-20mm
1.080
cft
175.00
189.00
Sub-Total(A1)
368.46
1208.92
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
2.640
cft
12.00
31.68
Brck flat soling
1.000
sft
5.00
5.00
CC Work
1.200
cft
35.00
42.00
150mm dia RCC Pipe
1.000
rft
25.00
25.00
Sub-Total(L1)
103.68
340.17
Total(1)
1549.09
Add over head on Total(1)
5.0 %
77.45
Total(2)
1626.55
Add Profit on Total(2)
10.0 %
162.65
Total(3)
1789.20
Add VAT on Unit Price
5.5 %
109.95
Add Income Tax on Unit Price
5.0 %
99.96
Unit Price
1999.11
Say
1999
per RM