BREAKDOWN OF UNIT PRICE
Item: (D01F) Coarse Agreegate Soling-200mm
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Sylhet
29.033
cft
65.00
1887.15
Stone-chips-19mm
58.066
cft
190.00
11032.54
Sub-Total(A1)
12919.69
1390.67
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Roller hire ch. i/c fuel
0.094
day
15000.00
1410.00
Sub-Total(E1)
1410.00
151.77
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sub-base Work/Gravel fiil
67.000
cft
20.00
1340.00
Sub-Total(L1)
1340.00
144.24
Total(1)
1686.68
Add over head on Total(1)
5.0 %
84.33
Total(2)
1771.02
Add Profit on Total(2)
10.0 %
177.10
Total(3)
1948.12
Add VAT on Unit Price
5.5 %
119.72
Add Income Tax on Unit Price
5.0 %
108.83
Unit Price
2176.67
Say
2177
per sqm