BREAKDOWN OF UNIT PRICE
Item: (D01E) Box Cutting- Filling Sand-500mm
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Filling Sand
217.000
cft
15.00
3255.00
Sub-Total(A1)
3255.00
350.37
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Roller hire ch. i/c fuel
0.117
day
15000.00
1755.00
Sub-Total(E1)
1755.00
188.91
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
167.000
cft
12.00
2004.00
Filling
167.000
cft
6.00
1002.00
Sub-Total(L1)
3006.00
323.57
Total(1)
862.84
Add over head on Total(1)
5.0 %
43.14
Total(2)
905.98
Add Profit on Total(2)
10.0 %
90.60
Total(3)
996.58
Add VAT on Unit Price
5.5 %
61.24
Add Income Tax on Unit Price
5.0 %
55.68
Unit Price
1113.50
Say
1114
per sqm