BREAKDOWN OF UNIT PRICE
Item: (C36A) MS Sliding Door
Basis:225 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
0.450
cft
35.00
15.75
Cement
1.000
bag
535.00
535.00
Brick-chips-20mm
0.900
cft
175.00
157.50
Sub-Total(A1)
708.25
33.88
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Enamel Painting -MS Dr/An
450.000
sft
15.00
6750.00
Sub-Total(S1)
6750.00
322.92
Total(1)
356.80
Add over head on Total(1)
5.0 %
17.84
Total(2)
374.64
Add Profit on Total(2)
10.0 %
37.46
Total(3)
412.11
Add VAT on Unit Price
5.5 %
25.33
Add Income Tax on Unit Price
5.0 %
23.02
Unit Price
460.45
Say
460
per SQM