BREAKDOWN OF UNIT PRICE
Item: (C17B) Roling Shutter 22 BWG-Both Option
Basis:300 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
0.613
cft
35.00
21.46
Cement
0.123
bag
535.00
65.81
Sub-Total(A1)
87.26
3.13
Total(1)
3.13
Add over head on Total(1)
5.0 %
0.16
Total(2)
3.29
Add Profit on Total(2)
10.0 %
0.33
Total(3)
3.62
Add VAT on Unit Price
5.5 %
0.22
Add Income Tax on Unit Price
5.0 %
0.20
Unit Price
4.04
Say
4
per m2