BREAKDOWN OF UNIT PRICE
Item: (C09) MS Angle Bar in Roof Frame
Basis:1 no.
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS angle
1.050
kg
72.00
75.60
Sub-Total(C1)
75.60
75.60
L5.Labour-MS Work
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Making Purlin,rafter, box
1.000
kg
8.00
8.00
Sub-Total(L5)
8.00
8.00
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Enamel Painting -MS Dr/An
0.457
sft
15.00
6.86
Sub-Total(S1)
6.86
6.86
Total(1)
90.46
Add over head on Total(1)
5.0 %
4.52
Total(2)
94.98
Add Profit on Total(2)
10.0 %
9.50
Total(3)
104.48
Add VAT on Unit Price
5.5 %
6.42
Add Income Tax on Unit Price
5.0 %
5.84
Unit Price
116.73
Say
117
per kg