BREAKDOWN OF UNIT PRICE |
Item: (C09) MS Angle Bar in Roof Frame |
Basis:1
no. |
|
C1.Steel Structures |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
|
MS angle |
1.050 |
kg |
72.00 |
|
|
|
|
Sub-Total(C1) |
75.60
|
75.60
|
|
L5.Labour-MS Work |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
|
Making Purlin,rafter, box |
1.000 |
kg |
8.00 |
|
|
|
|
Sub-Total(L5) |
8.00
|
8.00
|
|
S1.Sub-contractor-Civil |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
|
Enamel Painting -MS Dr/An |
0.457 |
sft |
15.00 |
|
|
|
|
Sub-Total(S1) |
6.86
|
6.86
|
|
|
|
|
Total(1) |
|
90.46
|
|
|
Add over head on Total(1)
|
5.0 % |
4.52
|
|
|
|
|
Total(2) |
|
94.98
|
|
|
Add Profit on Total(2)
|
10.0
% |
9.50
|
|
|
|
|
Total(3) |
|
104.48
|
|
|
Add VAT on Unit Price
|
5.5 % |
6.42
|
|
Add Income Tax on Unit Price
|
5.0 % |
5.84
|
|
|
|
|
Unit Price |
|
116.73
|
|
|
|
|
|
Say |
117 |
per kg |