BREAKDOWN OF UNIT PRICE
Item: (C05A) MS Ladder-50x50@600,37x37@300mm
Basis:3 no.
A3.Material-Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plastron Sealer
0.160
Ltr
370.00
59.20
Enamel paint
0.160
Ltr
355.00
56.80
Thinner-T6/T7
0.160
Ltr
120.00
19.20
Sub-Total(A3)
135.20
47.27
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS angle
153.000
kg
72.00
11016.00
Sub-Total(C1)
11016.00
3851.75
L6.Labour Paints
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Enamel Painting-Grl/Rai
64.000
sft
30.00
1920.00
Sub-Total(L6)
1920.00
671.33
Total(1)
4570.35
Add over head on Total(1)
5.0 %
228.52
Total(2)
4798.87
Add Profit on Total(2)
10.0 %
479.89
Total(3)
5278.75
Add VAT on Unit Price
5.5 %
324.39
Add Income Tax on Unit Price
5.0 %
294.90
Unit Price
5898.05
Say
5898
per each