BREAKDOWN OF UNIT PRICE
Item: (B15F8) Commode with Lowdown-RAK-White
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
White Cement-Elephant
1.000
kg
40.00
40.00
Sub-Total(A1)
40.00
40.00
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Commode- lowdon-RAK-White
1.000
no.
17200.00
17200.00
Sub-Total(B1)
17200.00
17200.00
B2.Sanitary fittings
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Flashing Equipment
1.000
no.
1000.00
1000.00
Nut with washer
4.000
no.
25.00
100.00
Sub-Total(B2)
1100.00
1100.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Commode fitting
1.000
no.
750.00
750.00
Sub-Total(L4)
750.00
750.00
Total(1)
19090.00
Add over head on Total(1)
5.0 %
954.50
Total(2)
20044.50
Add Profit on Total(2)
10.0 %
2004.45
Total(3)
22048.95
Add VAT on Unit Price
5.5 %
1354.96
Add Income Tax on Unit Price
5.0 %
1231.78
Unit Price
24635.70
Say
24636
per EACH