BREAKDOWN OF UNIT PRICE
Item: (B15F0) Long pan with Lowdown
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
0.500
cft
35.00
17.50
Cement
0.100
bag
535.00
53.50
Sub-Total(A1)
71.00
71.00
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
White Long Pan
1.000
no.
1520.00
1520.00
Lowdown-RAK-Asian
1.000
no.
2025.00
2025.00
Sub-Total(B1)
3545.00
3545.00
B2.Sanitary fittings
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
32mm PVC Waste Pipe
1.000
no.
360.00
360.00
PVC Connection Pipe
1.000
no.
160.00
160.00
Clamp-100mm
2.000
no.
40.00
80.00
Sub-Total(B2)
600.00
600.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Long Pan fitting
1.000
no.
750.00
750.00
Lowdown fitting
1.000
no.
475.00
475.00
Sub-Total(L4)
1225.00
1225.00
Total(1)
5441.00
Add over head on Total(1)
5.0 %
272.05
Total(2)
5713.05
Add Profit on Total(2)
10.0 %
571.31
Total(3)
6284.36
Add VAT on Unit Price
5.5 %
386.19
Add Income Tax on Unit Price
5.0 %
351.08
Unit Price
7021.63
Say
7022
per each