BREAKDOWN OF UNIT PRICE
Item: (B15E3) Wash Basin with Padestal-RAK
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
White Cement-Elephant
1.000
kg
40.00
40.00
Sub-Total(A1)
40.00
40.00
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Basin-Padestal-RAK-KARLA
1.000
no.
7135.00
7135.00
Sub-Total(B1)
7135.00
7135.00
B2.Sanitary fittings
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
32mm PVC Waste Pipe
1.000
no.
360.00
360.00
CI Bracket
1.000
pair
150.00
150.00
Grating with Brass Copuli
1.000
no.
300.00
300.00
CP Chain with rubber plug
1.000
no.
80.00
80.00
75mm Rowel Plug
2.000
no.
18.00
36.00
Sub-Total(B2)
926.00
926.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Basin fitting/Point
1.000
no.
680.00
680.00
Padestal Fixing
1.000
no.
200.00
200.00
Sub-Total(L4)
880.00
880.00
Total(1)
8981.00
Add over head on Total(1)
5.0 %
449.05
Total(2)
9430.05
Add Profit on Total(2)
10.0 %
943.01
Total(3)
10373.06
Add VAT on Unit Price
5.5 %
637.45
Add Income Tax on Unit Price
5.0 %
579.50
Unit Price
11590.01
Say
11590
per EACH