BREAKDOWN OF UNIT PRICE
Item: (B15E2) Wash Basin-Cabinate
Basis:1 no.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
0.050
cft
35.00
1.75
Cement
0.010
bag
535.00
5.35
Sub-Total(A1)
7.10
7.10
B2.Sanitary fittings
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
32mm PVC Waste Pipe
1.000
no.
360.00
360.00
Grating with Brass Copuli
1.000
no.
300.00
300.00
CP Chain with rubber plug
1.000
no.
80.00
80.00
Sub-Total(B2)
740.00
740.00
L4.Labour-Sanitary
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Basin fitting/Point
1.000
no.
680.00
680.00
Sub-Total(L4)
680.00
680.00
Total(1)
1427.10
Add over head on Total(1)
5.0 %
71.36
Total(2)
1498.46
Add Profit on Total(2)
10.0 %
149.85
Total(3)
1648.30
Add VAT on Unit Price
5.5 %
101.29
Add Income Tax on Unit Price
5.0 %
92.08
Unit Price
1841.68
Say
1842
per NO.