BREAKDOWN OF UNIT PRICE
Item: (A30E1) Pile DynamicLoad PDATest-100-300T
Basis:1 no.
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Skilled Labour
3.000
no
800.00
2400.00
Mason
1.000
no.
800.00
800.00
Foreman
1.000
no.
1000.00
1000.00
Electrician
1.000
no.
800.00
800.00
Sub-Total(L1)
5000.00
5000.00
Total(1)
5000.00
Add over head on Total(1)
5.0 %
250.00
Total(2)
5250.00
Add Profit on Total(2)
10.0 %
525.00
Total(3)
5775.00
Add VAT on Unit Price
5.5 %
354.89
Add Income Tax on Unit Price
5.0 %
322.63
Unit Price
6452.51
Say
6453
per each