BREAKDOWN OF UNIT PRICE
Item: (A25D1) Expansion Joint with Dowel Bar
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Sylhet
0.023
cft
65.00
1.50
Shaft Rod
0.500
kg
78.00
39.00
Bitumen
0.100
kg
75.00
7.50
Expansion Cap
3.500
no.
100.00
350.00
Sub-Total(A1)
398.00
1305.82
B1.Plumbing/Sanitr Pipe
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
PVC Pipe -20mm dia
1.000
rft
20.00
20.00
Sub-Total(B1)
20.00
65.62
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dowel Bar
0.500
kg
10.00
5.00
Expansion Joint making
1.000
rft
25.00
25.00
Sub-Total(L1)
30.00
98.43
Total(1)
1469.87
Add over head on Total(1)
5.0 %
73.49
Total(2)
1543.37
Add Profit on Total(2)
10.0 %
154.34
Total(3)
1697.70
Add VAT on Unit Price
5.5 %
104.33
Add Income Tax on Unit Price
5.0 %
94.84
Unit Price
1896.87
Say
1897
per RMT