BREAKDOWN OF UNIT PRICE
Item: (A25B8) Hollow Metal Door
Basis:25 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
0.613
cft
35.00
21.46
Cement
0.123
bag
535.00
65.81
Sub-Total(A1)
87.26
38.34
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Door Fitting
24.500
sft
35.00
857.50
Sub-Total(L1)
857.50
376.74
Total(1)
415.08
Add over head on Total(1)
5.0 %
20.75
Total(2)
435.83
Add Profit on Total(2)
10.0 %
43.58
Total(3)
479.41
Add VAT on Unit Price
5.5 %
29.46
Add Income Tax on Unit Price
5.0 %
26.78
Unit Price
535.66
Say
536
per Sq.m