Return Main Menu
BREAKDOWN OF UNIT PRICE
Item: (A25A2) MS Grill Square Bar i/c Paintimg
Basis:1 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
0.040
cft
35.00
1.40
Cement
0.010
bag
535.00
5.35
Sub-Total(A1)
6.75
72.66
A7.MS Work
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Grill Square bar
1.000
sft
280.00
280.00
Sub-Total(A7)
280.00
3013.92
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Fixing MS Window/ Grill
1.000
sft
15.00
15.00
Sub-Total(L1)
15.00
161.46
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Grill Paiting
1.000
sft
10.00
10.00
Sub-Total(S1)
10.00
107.64
Total(1)
3355.68
Add over head on Total(1)
5.0 %
167.78
Total(2)
3523.46
Add Profit on Total(2)
10.0 %
352.35
Total(3)
3875.81
Add VAT on Unit Price
5.5 %
238.18
Add Income Tax on Unit Price
5.0 %
216.53
Unit Price
4330.51
Say
4331
per SQM