BREAKDOWN OF UNIT PRICE
Item: (A25A) MS Window Grill
Basis:1 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
0.025
cft
35.00
0.88
Cement
0.005
bag
535.00
2.68
Sub-Total(A1)
3.55
38.21
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Fixing MS Window/ Grill
1.000
sft
15.00
15.00
Sub-Total(L1)
15.00
161.46
Total(1)
199.67
Add over head on Total(1)
5.0 %
9.98
Total(2)
209.66
Add Profit on Total(2)
10.0 %
20.97
Total(3)
230.62
Add VAT on Unit Price
5.5 %
14.17
Add Income Tax on Unit Price
5.0 %
12.88
Unit Price
257.68
Say
258
per M2