BREAKDOWN OF UNIT PRICE
Item: (A18A1) Demolition -RCC Stair Roof
Basis:1 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dismantling RCC
1.000
cft
100.00
100.00
Sub-Total(L1)
100.00
3531.50
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding-use 80 times
0.070
set
120.00
8.40
Sub-Total(M1)
8.40
296.65
Total(1)
3828.15
Add over head on Total(1)
5.0 %
191.41
Total(2)
4019.55
Add Profit on Total(2)
10.0 %
401.96
Total(3)
4421.51
Add VAT on Unit Price
5.5 %
271.71
Add Income Tax on Unit Price
5.0 %
247.01
Unit Price
4940.23
Say
4940
per M3