Return Main Menu
BREAKDOWN OF UNIT PRICE
Item: (A15A6) Insitu Pile Boring-600mm dia
Basis:1 rft
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bentonite
1.000
kg
30.00
30.00
Sub-Total(M1)
30.00
98.43
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Insitu Boring-600mm dia1
1.000
rft
500.00
500.00
Sub-Total(S1)
500.00
1640.50
Total(1)
1738.93
Add over head on Total(1)
5.0 %
86.95
Total(2)
1825.88
Add Profit on Total(2)
10.0 %
182.59
Total(3)
2008.46
Add VAT on Unit Price
5.5 %
123.43
Add Income Tax on Unit Price
5.0 %
112.20
Unit Price
2244.09
Say
2244
per RM