BREAKDOWN OF UNIT PRICE
Item: (A12B6) Plaster (1:4) 12mm thick NCF
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
7.500
cft
35.00
262.50
Cement
1.500
bag
535.00
802.50
Sub-Total(A1)
1065.00
114.64
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plaster Work
100.000
sft
18.00
1800.00
Neat Cement Finishing
100.000
sft
7.00
700.00
Sub-Total(L1)
2500.00
269.10
Total(1)
383.74
Add over head on Total(1)
5.0 %
19.19
Total(2)
402.92
Add Profit on Total(2)
10.0 %
40.29
Total(3)
443.22
Add VAT on Unit Price
5.5 %
27.24
Add Income Tax on Unit Price
5.0 %
24.76
Unit Price
495.21
Say
495
per SQM