Return Main Menu
BREAKDOWN OF UNIT PRICE
Item: (A12B1) Plaster (1:5) 12mm-Inner surface
Basis:100 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
7.500
cft
35.00
262.50
Cement
0.800
bag
535.00
428.00
Sub-Total(A1)
690.50
74.33
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Plaster Work
100.000
sft
18.00
1800.00
Sub-Total(L1)
1800.00
193.75
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding-use 80 times
0.500
set
120.00
60.00
Sub-Total(M1)
60.00
6.46
Total(1)
274.54
Add over head on Total(1)
5.0 %
13.73
Total(2)
288.26
Add Profit on Total(2)
10.0 %
28.83
Total(3)
317.09
Add VAT on Unit Price
5.5 %
19.49
Add Income Tax on Unit Price
5.0 %
17.71
Unit Price
354.29
Say
354
per M2