BREAKDOWN OF UNIT PRICE
Item: (A11RP) Door Shutter-Teak Chambal
Basis:21 sft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Door Shutter-Teak Chambal
1.000
no.
16000.00
16000.00
Sub-Total(A1)
16000.00
8401.17
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Door Shutter fixing
1.000
no.
600.00
600.00
Sub-Total(L1)
600.00
315.04
Total(1)
8716.21
Add over head on Total(1)
5.0 %
435.81
Total(2)
9152.03
Add Profit on Total(2)
10.0 %
915.20
Total(3)
10067.23
Add VAT on Unit Price
5.5 %
618.66
Add Income Tax on Unit Price
5.0 %
562.41
Unit Price
11248.30
Say
11248
per M2