BREAKDOWN OF UNIT PRICE
Item: (A11RN) Door Frame-Teak Chambal
Basis:2 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Door Frame-Teak Chambal
1.000
no.
5000.00
5000.00
Sub-Total(A1)
5000.00
117716.67
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Door Frame Fixing
1.000
no.
500.00
500.00
Sub-Total(L1)
500.00
11771.67
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Coaltaring 2 coats
8.665
sft
5.00
43.33
Door Clamp
4.000
no.
100.00
400.00
Sub-Total(M1)
443.33
10437.35
Total(1)
139925.68
Add over head on Total(1)
5.0 %
6996.28
Total(2)
146921.97
Add Profit on Total(2)
10.0 %
14692.20
Total(3)
161614.16
Add VAT on Unit Price
5.5 %
9931.60
Add Income Tax on Unit Price
5.0 %
9028.72
Unit Price
180574.48
Say
180574
per M3