BREAKDOWN OF UNIT PRICE
Item: (A10D5) Re-bar-Pile-Excluding-Re-bar
Basis:1000 kg.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Wire
8.000
kg
260.00
2080.00
Sub-Total(A1)
2080.00
2080.00
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding M/c
1000.000
kg
3.00
3000.00
Sub-Total(E1)
3000.00
3000.00
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar work-Substructure
1000.000
kg
8.00
8000.00
Sub-Total(L1)
8000.00
8000.00
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Welding Electrode VM 8-no
3.000
pack
750.00
2250.00
Sub-Total(M1)
2250.00
2250.00
Total(1)
15330.00
Add over head on Total(1)
5.0 %
766.50
Total(2)
16096.50
Add Profit on Total(2)
10.0 %
1609.65
Total(3)
17706.15
Add VAT on Unit Price
5.5 %
1088.09
Add Income Tax on Unit Price
5.0 %
989.17
Unit Price
19783.41
Say
19783
per ton