BREAKDOWN OF UNIT PRICE
Item: (A10A6) Re-bar Grade-60 in Superstructure
Basis:1000 kg.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Wire
5.000
kg
260.00
1300.00
Re-bar G60
1050.000
kg
101.50
106575.00
Sub-Total(A1)
107875.00
107875.00
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar work Superstructur
1000.000
kg
8.50
8500.00
Sub-Total(L1)
8500.00
8500.00
Total(1)
116375.00
Add over head on Total(1)
5.0 %
5818.75
Total(2)
122193.75
Add Profit on Total(2)
10.0 %
12219.38
Total(3)
134413.13
Add VAT on Unit Price
5.5 %
8260.02
Add Income Tax on Unit Price
5.0 %
7509.11
Unit Price
150182.26
Say
150182
per TON