BREAKDOWN OF UNIT PRICE
Item: (A10A5) Re-bar Grade 60 in Substructure
Basis:1000 kg.
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
GI Wire
8.000
kg
260.00
2080.00
Re-bar G60
1050.000
kg
101.50
106575.00
Sub-Total(A1)
108655.00
108655.00
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Re-bar work-Substructure
1000.000
kg
8.00
8000.00
Sub-Total(L1)
8000.00
8000.00
Total(1)
116655.00
Add over head on Total(1)
5.0 %
5832.75
Total(2)
122487.75
Add Profit on Total(2)
10.0 %
12248.78
Total(3)
134736.53
Add VAT on Unit Price
5.5 %
8279.90
Add Income Tax on Unit Price
5.0 %
7527.18
Unit Price
150543.60
Say
150544
per TON