BREAKDOWN OF UNIT PRICE
Item: (A09QF) Fenc-H=2.75m@2.4m c/c,Chnlnk-2.4m
Basis:96 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
8.910
bag
535.00
4766.85
Sand - Sylhet
22.275
cft
65.00
1447.88
Brick-chips-20mm
44.550
cft
175.00
7796.25
Re-bar G60
225.511
kg
101.50
22889.37
Sub-Total(A1)
36900.34
1261.15
C1.Steel Structures
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Plate-8mm
103.620
kg
60.00
6217.20
Sub-Total(C1)
6217.20
212.49
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
49.500
cft
4.00
198.00
Sub-Total(E1)
198.00
6.77
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
101.250
cft
12.00
1215.00
Filling
56.250
cft
6.00
337.50
RCC Work-Substructure
49.500
cft
40.00
1980.00
Form work-Substructure
180.000
sft
40.00
7200.00
Sub-Total(L1)
10732.50
366.81
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Shutter-Rent/ Used
180.000
sft
35.00
6300.00
Point Welding
150.000
poin
2.50
375.00
Electricity Cost
96.000
rft
0.50
48.00
Line Welding
100.480
inch
6.00
602.88
Sub-Total(M1)
7325.88
250.38
Total(1)
2097.58
Add over head on Total(1)
5.0 %
104.88
Total(2)
2202.46
Add Profit on Total(2)
10.0 %
220.25
Total(3)
2422.71
Add VAT on Unit Price
5.5 %
148.88
Add Income Tax on Unit Price
5.0 %
135.35
Unit Price
2706.93
Say
2707
per M