Return Main Menu
BREAKDOWN OF UNIT PRICE
Item: (A09Q7) Fencing-H=2.4ft@6ft c/c, Chainlin
Basis:100 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
2.869
cft
35.00
100.42
Cement
1.140
bag
535.00
609.90
Brick-chips-20mm
5.737
cft
175.00
1003.98
Sub-Total(A1)
1714.29
56.25
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
6.375
cft
4.00
25.50
Sub-Total(E1)
25.50
0.84
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
25.500
cft
12.00
306.00
Filling
19.125
cft
6.00
114.75
RCC Work-Substructure
6.375
cft
40.00
255.00
Form work-Substructure
51.000
sft
40.00
2040.00
Sub-Total(L1)
2715.75
89.10
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Shutter-Rent/ Used
51.000
sft
35.00
1785.00
Sub-Total(M1)
1785.00
58.57
Total(1)
204.75
Add over head on Total(1)
5.0 %
10.24
Total(2)
214.99
Add Profit on Total(2)
10.0 %
21.50
Total(3)
236.49
Add VAT on Unit Price
5.5 %
14.53
Add Income Tax on Unit Price
5.0 %
13.21
Unit Price
264.23
Say
264
per M