BREAKDOWN OF UNIT PRICE
Item: (A09Q3) Fencing-Chain Link-H=2.4m
Basis:100 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
17.600
bag
535.00
9416.00
Sand - Sylhet
34.400
cft
65.00
2236.00
Stone-chips-19mm
68.800
cft
190.00
13072.00
GI Wire
10.000
kg
260.00
2600.00
Sub-Total(A1)
27324.00
896.50
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
145.171
cft
4.00
580.68
Sub-Total(E1)
580.68
19.05
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth Work in Excavation
627.000
cft
12.00
7524.00
Filling
547.000
cft
6.00
3282.00
RCC Work-Substructure
80.000
cft
40.00
3200.00
Form work-Substructure
291.000
sft
40.00
11640.00
Sub-Total(L1)
25646.00
841.45
Total(1)
1757.00
Add over head on Total(1)
5.0 %
87.85
Total(2)
1844.85
Add Profit on Total(2)
10.0 %
184.48
Total(3)
2029.33
Add VAT on Unit Price
5.5 %
124.71
Add Income Tax on Unit Price
5.0 %
113.37
Unit Price
2267.41
Say
2267
per M