BREAKDOWN OF UNIT PRICE
Item: (A09F1) Demolition 250mm brick wall
Basis:1 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dismantle B/W 250mm thk
1.000
cft
35.00
35.00
Sub-Total(L1)
35.00
1236.03
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding-use 80 times
0.000
set
120.00
0.00
Sub-Total(M1)
0.00
0.00
Total(1)
1236.03
Add over head on Total(1)
5.0 %
61.80
Total(2)
1297.83
Add Profit on Total(2)
10.0 %
129.78
Total(3)
1427.61
Add VAT on Unit Price
5.5 %
87.73
Add Income Tax on Unit Price
5.0 %
79.75
Unit Price
1595.09
Say
1595
per M3