BREAKDOWN OF UNIT PRICE
Item: (A09) Demolition-RCC
Basis:1 cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Dismantling RCC
1.000
cft
100.00
100.00
Sub-Total(L1)
100.00
3531.50
Total(1)
3531.50
Add over head on Total(1)
5.0 %
176.58
Total(2)
3708.08
Add Profit on Total(2)
10.0 %
370.81
Total(3)
4078.88
Add VAT on Unit Price
5.5 %
250.66
Add Income Tax on Unit Price
5.0 %
227.87
Unit Price
4557.41
Say
4557
per M3