BREAKDOWN OF UNIT PRICE
Item: (A08P7) RCC(1:1.25:2.5) Form,Sylhet-GF
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
25.263
bag
535.00
13515.71
Sand - Sylhet
40.000
cft
65.00
2600.00
Stone-chips-19mm
80.000
cft
190.00
15200.00
Sub-Total(A1)
31315.71
11059.14
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
4.00
400.00
Sub-Total(E1)
400.00
141.26
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work-Substructure
100.000
cft
40.00
4000.00
Form work-Substructure
6.632
sft
40.00
265.28
Sub-Total(L1)
4265.28
1506.28
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Shutter-Rent/ Used
6.632
sft
35.00
232.12
Sub-Total(M1)
232.12
81.97
Total(1)
12788.66
Add over head on Total(1)
5.0 %
639.43
Total(2)
13428.09
Add Profit on Total(2)
10.0 %
1342.81
Total(3)
14770.90
Add VAT on Unit Price
5.5 %
907.71
Add Income Tax on Unit Price
5.0 %
825.19
Unit Price
16503.80
Say
16504
per CUM