BREAKDOWN OF UNIT PRICE
Item: (A08M8) Insitu Pile-600mm dia 10m-Extra
Basis:1 rft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
0.736
bag
535.00
393.76
Sand - Sylhet
1.389
cft
65.00
90.29
Stone-chips-19mm
2.777
cft
190.00
527.63
Re-bar G60
8.348
kg
101.50
847.32
Sub-Total(A1)
1859.00
6099.37
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bentonite
0.500
kg
30.00
15.00
Point Welding
6.000
poin
2.50
15.00
Sub-Total(M1)
30.00
98.43
S1.Sub-contractor-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Insitu Boring-600mm dia
1.000
rft
2000.00
2000.00
Sub-Total(S1)
2000.00
6562.00
Total(1)
12759.80
Add over head on Total(1)
5.0 %
637.99
Total(2)
13397.79
Add Profit on Total(2)
10.0 %
1339.78
Total(3)
14737.57
Add VAT on Unit Price
5.5 %
905.66
Add Income Tax on Unit Price
5.0 %
823.33
Unit Price
16466.56
Say
16467
per RM