BREAKDOWN OF UNIT PRICE
Item: (A08EZ) RCC-C30-Pile Cap, i/c Shutter-Tra
Basis:149 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
37.720
bag
535.00
20180.20
Sand - Sylhet
59.750
cft
65.00
3883.75
Stone-chips-19mm
119.500
cft
190.00
22705.00
Sub-Total(A1)
46768.95
11056.67
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
149.380
cft
4.00
597.52
Sub-Total(E1)
597.52
141.26
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work-Substructure
149.380
cft
40.00
5975.20
Form work-Substructure
79.220
sft
40.00
3168.80
Pile Head Breaking
38.040
cft
120.00
4564.80
Sub-Total(L1)
13708.80
3240.90
Total(1)
14438.83
Add over head on Total(1)
5.0 %
721.94
Total(2)
15160.78
Add Profit on Total(2)
10.0 %
1516.08
Total(3)
16676.85
Add VAT on Unit Price
5.5 %
1024.83
Add Income Tax on Unit Price
5.0 %
931.67
Unit Price
18633.36
Say
18633
per Cum