BREAKDOWN OF UNIT PRICE
Item: (A08E2) RCC(1:2:4), Brick-chips-Substruct
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
22.500
cft
35.00
787.50
Cement
18.000
bag
535.00
9630.00
Sand - Sylhet
22.500
cft
65.00
1462.50
Brick-chips-20mm
90.000
cft
175.00
15750.00
Sub-Total(A1)
27630.00
9757.53
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
4.00
400.00
Sub-Total(E1)
400.00
141.26
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work-Substructure
100.000
cft
40.00
4000.00
Sub-Total(L1)
4000.00
1412.60
Total(1)
11311.39
Add over head on Total(1)
5.0 %
565.57
Total(2)
11876.96
Add Profit on Total(2)
10.0 %
1187.70
Total(3)
13064.66
Add VAT on Unit Price
5.5 %
802.86
Add Income Tax on Unit Price
5.0 %
729.87
Unit Price
14597.39
Say
14597
per M3