BREAKDOWN OF UNIT PRICE
Item: (A08E0) RCC(1:1.25:2.5) Form,Sylhet-Footn
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
25.263
bag
535.00
13515.71
Sand - Sylhet
40.000
cft
65.00
2600.00
Stone-chips-19mm
80.000
cft
190.00
15200.00
Sub-Total(A1)
31315.71
11059.14
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
4.00
400.00
Sub-Total(E1)
400.00
141.26
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC Work-Substructure
100.000
cft
40.00
4000.00
Form work-Substructure
64.000
sft
40.00
2560.00
Sub-Total(L1)
6560.00
2316.66
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Shutter-Rent/ Used
64.000
sft
35.00
2240.00
Sub-Total(M1)
2240.00
791.06
Total(1)
14308.12
Add over head on Total(1)
5.0 %
715.41
Total(2)
15023.53
Add Profit on Total(2)
10.0 %
1502.35
Total(3)
16525.88
Add VAT on Unit Price
5.5 %
1015.56
Add Income Tax on Unit Price
5.0 %
923.23
Unit Price
18464.67
Say
18465
per M3