BREAKDOWN OF UNIT PRICE
Item: (A08DV) Form Work-Plywood Precast
Basis:100 sft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Form work-Substructure
100.000
sft
40.00
4000.00
Sub-Total(L1)
4000.00
430.56
Total(1)
430.56
Add over head on Total(1)
5.0 %
21.53
Total(2)
452.09
Add Profit on Total(2)
10.0 %
45.21
Total(3)
497.30
Add VAT on Unit Price
5.5 %
30.56
Add Income Tax on Unit Price
5.0 %
27.78
Unit Price
555.64
Say
556
per M2