BREAKDOWN OF UNIT PRICE
Item: (A08DT) RCC(1:2:4) Form,Brick,Sylh-Lintel
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement
18.000
bag
535.00
9630.00
Sand - Sylhet
45.000
cft
65.00
2925.00
Brick-chips-20mm
90.000
cft
175.00
15750.00
Sub-Total(A1)
28305.00
9995.91
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
4.00
400.00
Sub-Total(E1)
400.00
141.26
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC work Super-structure
100.000
cft
40.00
4000.00
Form work Super-structure
123.913
sft
35.00
4336.96
Sub-Total(L1)
8336.96
2944.20
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Shutter-Rent/ Used
123.913
sft
35.00
4336.96
Sub-Total(M1)
4336.96
1531.60
Total(1)
14612.96
Add over head on Total(1)
5.0 %
730.65
Total(2)
15343.61
Add Profit on Total(2)
10.0 %
1534.36
Total(3)
16877.97
Add VAT on Unit Price
5.5 %
1037.19
Add Income Tax on Unit Price
5.0 %
942.90
Unit Price
18858.07
Say
18858
per CUM