BREAKDOWN OF UNIT PRICE
Item: (A08DK) RCC(1:1.5:3) Brck,L:S=1:1-Bontek
Basis:100 cft
A1.Materials-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand - Local
21.500
cft
35.00
752.50
Cement
22.000
bag
535.00
11770.00
Sand - Sylhet
21.500
cft
65.00
1397.50
Brick-chips-20mm
86.000
cft
175.00
15050.00
Sub-Total(A1)
28970.00
10230.76
E1.Equipment-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c and vibrator
100.000
cft
4.00
400.00
Sub-Total(E1)
400.00
141.26
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
RCC work Super-structure
100.000
cft
40.00
4000.00
Sub-Total(L1)
4000.00
1412.60
Total(1)
11784.62
Add over head on Total(1)
5.0 %
589.23
Total(2)
12373.85
Add Profit on Total(2)
10.0 %
1237.38
Total(3)
13611.23
Add VAT on Unit Price
5.5 %
836.44
Add Income Tax on Unit Price
5.0 %
760.40
Unit Price
15208.08
Say
15208
per CUM