BREAKDOWN OF UNIT PRICE
Item: (A08D7) Form Work for RCC -Superstructure
Basis:100 sft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Form work Super-structure
100.000
sft
35.00
3500.00
Sub-Total(L1)
3500.00
376.74
M1.Misc.-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding-use 80 times
0.500
set
120.00
60.00
Shutter-Rent/ Used
100.000
sft
35.00
3500.00
Sub-Total(M1)
3560.00
383.20
Total(1)
759.94
Add over head on Total(1)
5.0 %
38.00
Total(2)
797.94
Add Profit on Total(2)
10.0 %
79.79
Total(3)
877.73
Add VAT on Unit Price
5.5 %
53.94
Add Income Tax on Unit Price
5.0 %
49.04
Unit Price
980.70
Say
981
per M2